Quang Ninh aims to complete public investment disbursement in December

Chia sẻ
(VOVWORLD) - Quang Ninh had disbursed more than 280 million USD by the end of November, or 62.5% of the target assigned by the Prime Minister. 
Quang Ninh aims to complete public investment disbursement in December - ảnh 1Remote construction sites run four shifts around the clock. (Photo: baoquangninh.vn)
 
 The province plans to disburse at least 174 million USD more in December to reach 100% for 2025.

Quang Ninh’s total public investment in 2025 is now 647 million USD, over 193 million USD more than the initial plan. The province has cleared land, material, and planning issues, allowing investors and contractors to work extra hours and add equipment.

The disbursement of provincial projects in Quang Ninh has reached 196 million USD out of 388 million USD while the projects transferred from the district level are speeding up for December. Key works including Van Ninh Port and the Van Don – Mong Cai Expressway link, are being worked on continuously to build the new logistics hub. Many contractors run three or four shifts. Nine riverside road projects on the Ha Long – Hai Phong Expressway aim to finish over 10 km of road and spend more than 13.2 million USD this month.